Machinery Regulation guide

Deadlines and transition: what must happen by 20 January 2027

A hard cut-off date instead of a transition period: from 20 January 2027, every placing on the market is governed exclusively by the Machinery Regulation.

In short

Regulation (EU) 2023/1230 applies from 20 January 2027 with no transition period (Art. 54 as corrected, OJ L 169 of 4 July 2023). What counts is the placing on the market or putting into service of the individual machine, not the order, design or year of construction. Until 19 January 2027 only Directive 2006/42/EC applies, from 20 January only the Regulation. Machinery lawfully placed on the market before that date remains marketable; there is no retrofitting obligation.

The cut-off date: 20 January 2027

Regulation (EU) 2023/1230 already entered into force in July 2023 — it becomes mandatory from 20 January 2027. From that day on, it applies to every placing of machinery on the market within the European Economic Area. The current Machinery Directive 2006/42/EC is repealed at the same moment.

The principle behind this matters: there is no parallel regime and no transition period. Until 19 January 2027, the Machinery Directive applies exclusively; from 20 January 2027, the EU Machinery Regulation applies exclusively. A machine cannot be placed on the market "optionally" under one legal basis or the other.

What happens to existing machinery

Machinery lawfully placed on the market under the Machinery Directive before the cut-off date remains marketable. It may continue to be operated, resold and made available — the cut-off date creates no obligation to retrofit existing machinery to Machinery Regulation level.

Caution is needed with modifications: anyone who substantially modifies existing machinery can legally become the manufacturer — with all the obligations of the Machinery Regulation then in force, from the risk assessment through to a new EU declaration of conformity. What counts as a substantial modification is covered on our page on the substantial modification of machinery.

Backward planning for machine builders

What matters is not the order date but the moment of placing on the market. A machine ordered in 2026 but delivered only after 20 January 2027 must fully comply with the Machinery Regulation — including its documentation obligations.

In practice this means: projects with delivery dates around the cut-off should already be documented according to the requirements of the Machinery Regulation today. Converting documentation processes takes lead time: digital operating instructions, maintaining document editions, long-term provision. Those who start now gain the buffer that special-purpose machinery and plant engineering with long project durations need anyway.

Backward planning in six steps

Counting back from the cut-off date gives an order that most companies can work through in two to three quarters:

  • By Q4/2026: identify all projects delivered from 20 January 2027 — they need a declaration of conformity, operating manual and technical documentation under the Regulation.
  • Switch templates: declaration of conformity to Annex V Part A, declaration of incorporation to Annex V Part B, legal references in manual and documentation.
  • Extend the risk assessment: cybersecurity of networked safety functions and, where relevant, self-evolving control systems (Annex III 1.1.9 and 1.2.1).
  • Check Annex I: machinery in Part A requires a notified body, with lead time.
  • Decide on delivery: digital manual under Art. 10(7), then organise access details on the machine, ten-year availability and the paper-on-request process.
  • Define a process for substantial modifications, since the definition in Art. 3(16) also covers digital changes.

FAQ

Frequently asked questions

Is there a transition period for the Machinery Regulation?

No. The Machinery Regulation applies from 20 January 2027 as a hard cut-off rule: before that date, the Machinery Directive 2006/42/EC applies exclusively; from the cut-off date, Regulation (EU) 2023/1230 applies exclusively.

May I still deliver a machine ordered in 2026 under the Machinery Directive in 2027?

No. The decisive moment is the placing on the market, not the order. If delivery takes place after 20 January 2027, the machine must comply with the EU Machinery Regulation.

Does the Machinery Regulation also apply to partly completed machinery?

Yes. Partly completed machinery also falls under the Regulation — with a declaration of incorporation and assembly instructions instead of an EU declaration of conformity and operating instructions.

Keep reading

More chapters of this guide

Digital Operating Instructions under the Machinery Regulation: What Is Permitted

Paper is no longer mandatory: Article 10(7) permits digital operating instructions, subject to conditions.

Technical Documentation under the Machinery Regulation: Scope, Retention, Access

From risk assessment to declaration of conformity: what must remain deliverable for 10 years — and what may stay protected.

QR Code on the Machine: What Art. 10(7) Requires

The Machinery Regulation does not prescribe a QR code. For digital instructions, however, it requires access information on the machine.

Declaration of Conformity under the Machinery Regulation: What Changes on 20 January 2027

The legally binding document behind the CE marking: what belongs in it — and what changes on 20 January 2027.

Risk Assessment under the Machinery Regulation: Obligation, Process, Documentation

No CE marking without a risk assessment: the process according to ISO 12100 — and the new Machinery Regulation requirements from cybersecurity to AI.

Machinery Directive vs. Machinery Regulation: All Differences Compared

Directive 2006/42/EC applies until 19 January 2027, Regulation (EU) 2023/1230 from 20 January 2027 onwards. The comparison point by point, and what it means for documentation, the declaration of conformity and the operating manual.

Substantial Modification of Machinery under the Machinery Regulation: Definition, Consequences, Obligations

Defined by law for the first time: Art. 3(16) says when a modification is substantial, and Art. 18 what follows.

Next step

Check your Machinery Regulation readiness — or start right away.